[Dec-2024] Dumps Practice Exam Questions Study Guide for the C_S4PPM_2021 Exam
C_S4PPM_2021 Dumps with Practice Exam Questions Answers
SAP S/4HANA Portfolio and Project Management module is a powerful tool that allows organizations to manage their projects, resources, and finances in a single integrated platform. With this module, companies can plan, execute, and monitor their projects with greater efficiency and accuracy, while also gaining better visibility into their project portfolios. The SAP C-S4PPM-2021 exam is designed to ensure that professionals have the knowledge and expertise required to effectively use this module.
SAP C-S4PPM-2021 exam is ideal for professionals who work with SAP S/4HANA PPM, such as project managers, portfolio managers, business analysts, and consultants. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification can help professionals demonstrate their expertise in SAP S/4HANA PPM and enhance their career opportunities. As SAP S/4HANA continues to gain popularity, the demand for certified professionals is expected to increase, making the SAP C-S4PPM-2021 certification a valuable asset for professionals in this field.
SAP C_S4PPM_2021 certification exam is a must-have certification for SAP professionals who are involved in project and portfolio management using the SAP S/4HANA platform. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification exam validates the candidate's skills and knowledge in managing portfolios and projects using SAP S/4HANA, making them highly desirable to potential employers.
NEW QUESTION # 48
Your client wants to add additional checklist items to a project that has already began.
They want to control the items separately as unplanned.
Which setting must you make in customizing?
- A. Create a checklist type and set the issue list indicator
- B. Create a checklist item type and assign to the project type
- C. Create a checklist type and assign a new status Unplanned
- D. Create a checklist item type and set the issue item indicator
Answer: C
NEW QUESTION # 49
Which of the following can be viewed in the item dashboard? NOTE: There are 3 correct answers to this question.
- A. authorizations
- B. Documents
- C. metrics
- D. Custom fields
- E. Standard fields
Answer: B,D,E
NEW QUESTION # 50
You are planning resources.
Which period types are available?
NOTE: There are 3 correct answers to this question.
- A. Daily
- B. Weekly
- C. Hourly
- D. Monthly
Answer: B,D
NEW QUESTION # 51
You staff a resource to a project.
Where is the default authorization for the resource defined?
- A. In customizing for role types
- B. In customizing for role functions
- C. In the project
- D. In the project template
Answer: A
NEW QUESTION # 52
How are capacity planning values rolled up along the bucket hierarchy?
- A. Item values are rolled up directly to buckets
- B. Item values are rolled up to buckets via the collection
- C. Item values are rolled up to buckets via the review
- D. Project values are rolled up directly to buckets
Answer: A
NEW QUESTION # 53
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this? NOTE: There are 2 correct answers to this question
- A. You are not defined as the project Responsible
- B. Milestone is not identified as mandatory
- C. Project is not released
- D. Milestone is not identified as critical
Answer: A,C
NEW QUESTION # 54
Which of the following can you use to create multiple portfolio items simultaneously?
- A. Item template
- B. Microsoft Excel import
- C. Microsoft project import
- D. Primavera import
Answer: A
NEW QUESTION # 55
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question
- A. Item currency can be inherited from the assigned bucket
- B. Multiple planning currencies can be used in one bucket
- C. Items In a bucket an only use bucket currencies
- D. Bucket in a portfolio can use different currencies
Answer: A,D
NEW QUESTION # 56
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to tasks that have the in process status
- B. Your personal number is not assigned to a business partner
- C. Your role and business partner are assigned to task that have the created status
- D. Your user is not assigned to a business partner
Answer: B,C
NEW QUESTION # 57
Which information can be assigned to a business partner in project management? NOTE: There are 3 correct answers to this question
- A. Production resources or tools (PRT)
- B. Work centers
- C. Personal numbers
- D. Areas and locations
- E. SAP users
Answer: B,D,E
NEW QUESTION # 58
What must you configure to view portfolio item data in project management projects?
- A. Set the portfolio management flag to active in customizing for the project type
- B. Set the objects link flag to active in customizing for the project management structure
- C. Set the business content data source for portfolio management in customizing
- D. Set the project management flag to active in customizing for the linking item type
Answer: A
NEW QUESTION # 59
In project management, a WBS element for accounting integration was created automatically.
What is used to calculate the planned costs of this WBS element?
NOTE: There are 3 correct answers to this question
- A. Demand planned on project roles
- B. Work planned on project task
- C. Staffing of work in the role
- D. Duration planned on project tasks
Answer: A,B
NEW QUESTION # 60
What features does SAP analytics cloud deliver in combination with SAP PPM? NOTE: There are 3 correct answers to this question.
- A. Out-of-the-box cost commitment reporting capabilities
- B. Intelligent algorithms highlighting possible data quality issues and distributing your data
- C. Built-in connectors to data sources
- D. Provides models for financial and capacity planning
- E. Smart transformations enabling you to quickly address and solve data quality issues
Answer: A,C,D
NEW QUESTION # 61
What influences whether an items is displayed in a specific dashboard scope?
NOTE: There are 3 correct answers to this question
- A. Priority
- B. Item status group
- C. Proposal flag
- D. Escalation flag
- E. Decision point status
Answer: B,C,D
NEW QUESTION # 62
In portfolio management to which of the following does the logical system refer In the definition of the PS project definition object link?
- A. BCV system for reporting
- B. Web server for integration
- C. Target system for integration
- D. Business intelligence (BI) system for reporting
Answer: C
NEW QUESTION # 63
When you create an item from an initiative, which of the following objects are authorizations inherited from? NOTE: There are 3 correct answers to this question
- A. Portfolio
- B. Project management project
- C. initiative
- D. Project system project
- E. Parent bucket
Answer: A,C,E
NEW QUESTION # 64
A WBS element has been created automatically for a project management project. A change is made to the organizational unit of the project definition.
When is the master data of the internal order updated with the change?
- A. Upon release of the project
- B. Upon release of the WBS element
- C. Upon the next cost planning run
- D. Upon the next transfer
Answer: D
NEW QUESTION # 65
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing? NOTE: There are 2 correct answers to this question
- A. The complete phase when Granting Approval indicator
- B. The completion required indicator
- C. The approval phase indicator
- D. The Release Success phase only after Approval indicator
Answer: B,D
NEW QUESTION # 66
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A. Role assignment and staffing
- B. Qualification determination
- C. Extended staffing
- D. Staffing by authorization
Answer: C
NEW QUESTION # 67
You want to distribute capacity requirements in a project management project?
How can you distribute the values? NOTE: There are 3 correct answers to this question
- A. Update the capacity requirements from the roll-up of task requirements
- B. Use a distribution function
- C. Copy values from resource assignments
- D. Apply a distribution rule
- E. Enter the vales manually
Answer: B,D,E